Home

 

 

URS-Cash-&-Associates-PMS.gif (5518 bytes)

DESIGN/BUILD PROJECTS

Cash & Associates design/build experience includes the preparation of design/build solicitation (Invitation to Bid) documents and engineering and architectural design services as a member of a design/build team.  Examples of our experience follow.


Lonestar-1.jpg (18575 bytes)IMPORT CEMENT MARINE TERMINAL
Port of Redwood City, California

Cash & Associates provided civil and structural engineering for this design/build project with Manson Construction that involved construction of a new $10M cement terminal to replace an existing outmoded facility.  Project components included a new concrete pier; concrete pile-supported platform for the ship unloader; stationary 800-ton per hour cement unloader mounted on a fixed pier; 650' long conveyor system (from ship to cement silo); eight berthing/mooring dolphins with marine fenders for mooring cement import ships; 20' wide bridge to provide access for maintenance, operation, fire trucks and other vehicles; access catwalk to berthing/mooring dolphins; pier utilities; and dredging.

Lonestar-2.jpg (29026 bytes)

The new facility accommodates post-Panamax vessels and provides the capability to handle approximately 843,000 tons of imported cement annually.  With an unload rate of 800 tons per hour, the terminal allows calling vessels carrying 30,000 to 53,000 tons of cargo to complete unloading operations within 3 to 5 days compared to the previous 12 to 15 days for the old facility.  This improved unloading capability provides significant cost savings.

*See Piers/Wharves and Bulk Terminals for other photographs of this project.




PROCESSING & DISTRIBUTION CENTER EXPANSIONS
United States Postal Service, San Jose & Fresno, California

usps-inside.jpg (128761 bytes)Cash & Associates provided architectural design, civil and structural engineering for a Design/Build Project involving expansion of two existing USPS processing and distribution centers.  Expansion of the San Jose facility included a 40,450 SF addition that extended an existing workroom area into a parking lot and added new men's and women's restrooms.  The expansion involved a 30' high, single story structure repeating the existing facility's architectural theme of concrete tilt-up walls with a combination of ceramic tile finish and painted panels with modulated joints and reveals.  Special design considerations included the facility's proximity to the San Andreas, Hayward and Calaveras Earthquake Faults.  The Fresno facility expansion involved an addition of 29,450 SF for workroom space, and new men's and women's restrooms.  The expanded workroom areas provide additional space to accommodate new automated processing equipment.  All work was performed under a fast-track design/build schedule.

 

NASSCO_Aerial.jpg (57227 bytes)NASSCO BLOCK ASSEMBLY LINE
San Diego, California

Provided A-E services for tenant improvements for facilitate installation of new "Block Assembly Line" equipment at National Steel and Shipbuilding Co.  Cash & Associates was responsible for architecture and structural and civil engineering.  The Block Assembly Line is similar to a conveyor belt operation during which steel plates and other shapes are welded together to form large blocks (approx. 20' by 30' weighing 300 metric tons) that are used to construct ship hulls.  This project included demolition of three existing buildings and relocation of various shipyard operations to provide space for the new Block Assembly Line.  The project site was severely constricted and congested due to existing buildings, utilities and other structures.  Extensive site investigations and safety and fire code reviews were conducted to develop creative design solutions that took could take advantage of existing construction, as well as other methods that achieved code compliance for area separations.  To mitigate the potential for thermal expansion, it was solar shading studies were prepared to ensure placement of equipment out of the path of direct sunlight from skylights and building openings.  New buildings included: Block Assembly Line, Pipe Shop, Main Shop and Hazardous Storage, Compressor, Covered Work Area, Maintenance, Oil Storage, and Steam Cleaning.  Provisions to accommodate several large gantrys (i.e., 150' high, 200 metric ton turnover) used to transport completed blocks were incorporated as well.   Structural design included building and equipment foundations and anchorage for cranes, conveyors and other equipment.  Civil design included site grading and extensive underground utilities and vaults.


Piers10-11-Aerial-2.JPG (1573782 bytes)
REPLACE PIERS 10 & 11
Naval Station, San Diego, California

The Harris/Cash Joint Venture (DMJM Harris/Cash & Associates) was selected to provide multidiscipline consulting services for preparation of design and construction documents to be used by the Navy for a Design/Build Solicitation package for construction of a new $38M berthing/maintenance pier at the Naval Station, San Diego, California.  The project involves demolition of two existing piers, dredging, and design of a new permanent 36M by 457.3M concrete berthing/maintenance pier capable of supporting multiple Navy vessels and the unrestricted use of a 90-ton crane.  The pier will have "cold iron" capability with a concrete and plastic fendering system featuring foam-filled fenders and plastic camels.  Pier utilities include freshwater, wastewater, compressed air, oily waste, electrical, fire alarms, cable TV, EMC/SCADA system, fiber optics to support a computer network, and lighting.






Pier D-7.jpg (55901 bytes)
PIER D MARGINAL WHARF
Port of Long Beach, California

Cash & Associates provided complete structural engineering and project management for this design/build project involving construction of a new reinforced concrete wharf, demolition of two existing timber wharves, development of dredging requirements, permitting services, and construction phase support.  The new wharf supports berthing of multiple tugboats and construction staging operations for a local marine contractor.



Home ]

Last modified: January 11, 2007