|

| |

Raytheon Systems Company/Hughes Aircraft
Company
Since 1976, Cash & Associates has
provided Architect-Engineer Services to Raytheon Systems Company (formerly Hughes Aircraft
Company) for individual projects, projects under continuous open-end contracts, and
design/build projects in the United States and overseas. Over 1,000 projects,
including new designs, tenant improvements, and site work, have been completed.
Projects have included company-owned, private and government-owned leased facilities, and
modifications to Government-owned facilities. Facilities have included offices,
conference and administrative facilities; special environments (i.e., SCIF, environmental
and anechoic chambers, cleanrooms); computer simulation and data processing facilities;
manufacturing, production and testing facilities; antenna towers; warehouses and shops;
shipping and receiving facilities; lunch and break room facilities; equipment
installations; chiller plants and cooling towers; hazmat/chemical storage facilities;
material handling equipment (i.e., cranes, conveyors); mezzanines; canopies; security
stations; emergency/UPS power; plant fire station/emergency incident response center, and
various plant infrastructure (i.e., roads, parking lots, test track) projects. Many
projects have required the incorporation of DoD Secure facility measures. Our most
recent work has involved facility relocations and consolidations. Examples of our work
follow:
RELOCATE RADAR TEST & CALIBRATION OPERATIONS
Thales
Raytheon, Fullerton, California
Prime
Consultant responsible for project management, structural and civil engineering, cost
estimating, contract document preparation, coordination of subconsultant work, and
construction support services to relocate radar test and calibration operations facilities
to a previously undeveloped 2.5 acre parcel. Project included a new 9,500 SF
pre-engineered metal building, foundations for the building and a 90 high radar
tower, relocation of a 750 SF thermal chamber, and demolition of an existing building.
Design also included a high bay rain test area with spray, storage tank and pumping
equipment. Building design incorporated measures for noise control. Civil design
included rough and final grading plans, paving and striping plans (including over 1,100
parking spaces), as well as sewer connection and domestic and fire protection water lines.
Facility amenities included office support areas, a compressed air piping system,
fire sprinkler system, HVAC with temperature and humidity controls, compressed air,
furnaces, lighting and power systems, 400Hz generators. Facility security measures
included a monitored fence line. C&As Project Manager, David Bachle,
worked closely with Thales Raytheon staff and City of Fullerton officials to resolve
complex project-specific issues. Scheduling was developed to allow continued facility
operations during construction.
BUILDINGS H1-H4 TENANT IMPROVEMENTS
Sensors and
Electronic Systems (E-Systems), Goleta, California
Cash & Associates provided comprehensive architectural and structural design, and
project management services to consolidate two existing E-Systems campuses into a single
site on Hollister Avenue. Consolidation involved relocating the management and
administrative groups from a two building campus to the four building Hollister Avenue
site. All work involved fast-track design and construction scheduling. An
important design consideration was to provide new management facilities within an existing
building constructed in the 1950's that were equal to or better than the more recently
constructed buildings being vacated. Work involved complete demolition of all
existing interior improvements and approximately 179,00 SF of new interior improvements
including the addition of 4,000 SF. Complete exterior (facade) remodel and
redesign was undertaken for all buildings including the selection of all interior and
exterior finishes and materials. Design criteria included creating new executive
office space in an older building that was equal to or better than the newer buildings
that were vacated.
The Hollister
Avenue Campus is located in an area subject to strict criteria that requires the overall
character and appearance of all buildings to be in compliance with long term local
government goals for the area. To modify and upgrade building exteriors, it was
necessary to obtain special approvals from the County of Santa Barbara. Project
components included a new Class 100,000 cleanroom and anechoic
chamber, government property shipping/receiving areas, systems
integration and test areas, various assembly and lab spaces, paint shop, metrology area,
offices, conference rooms, cafeteria and kitchen facilities, and miscellaneous support
facilities. Structural design included interior modifications and new structural
steel raised platforms to support extensive roof-mounted equipment requirements. To
achieve Raytheon's fast-track construction schedule goals, Cash & Associates provided
on-site construction support services to expedite responses to Contractor questions and
submittals.
CDTE
FACILITY
Infrared Center of Excellence, Goleta, California
Work at the IrCoE facility has involved modifications to existing buildings. An
example of recent work is the CdTe Facility. This project involved modifications to
an existing chemical storage building to create a facility for development and manufacture
of specialty composite materials for use in electronic components. The
manufacturing process involves the reaction of molten two compounds that form the CdTe
compound. This reaction, under upset conditions, has the potential for deflagration.
In addition to building modifications to create this facility, requirements for the
incorporation and installation of specially designed pressure vessels that remove air
(oxygen) were developed. Existing chemical storage facilities were relocated to another
area of the building, as well.
BUILDING H5
CONCEPTUAL DESIGN
E-Systems, Goleta, California
Architectural design and engineering for conceptual design and preparation of Preliminary
Concept Layout and elevations for a proposed 50,000 SF office/laboratory building.
Design considerations included site specific geotechnical and environmental conditions
requiring special foundation design solutions. Proposed design minimized the number
of columns and corresponding foundations to produce an efficient, cost-effective structure
with a flexible internal floor plan that support Raytheon's desire for an open office
plan. Building elevations were selected to compliment the design of an existing,
adjacent building. Proposed construction included Portland cement stucco over steel
studs with an extended roof overhang providing shading to compliment solar glazing.
RELOCATE SURTASS PROGRAM
FACILITIES
Fullerton, California to Portsmouth, Rhode Island
Comprehensive architectural design services for relocation of Surface to Air Surveillance
System (SURTASS) Program facilities from Fullerton, California (original facility designed
by C&A) to Raytheon's Integrated Ocean Systems complex in Portsmouth, Rhode
Island. Project involved fast-track design of interior modifications to an existing
building to create high-tech, top secret (classified) facilities including labs, testing
areas, offices and computer rooms. Building interior finishes were replaced and
building exterior was brought into compliance with current ADA requirements. The
existing electrical system was replaced to provide new systems tailored to provide
shipboard, aircraft and conventional power. Facilities were designed to allow
future expansion of production capacity and personnel.
BUILDINGS R7 & 49 RECCE PROGRAM FACILITIES
Sensors and Electronic Systems, El Segundo, California
As part of the Hughes/Raytheon facility consolidation, the RECCE Program electronic
manufacturing/testing facilities were relocated to new climate controlled space with
humidity sensitive requirements. The project involved interior modifications to five
separate floors (76,913 SF) within two existing high rise buildings. Work included
interior rearrangement/relocation to convert existing office spaces into SECURE laboratory
facilities. New facilities included machine shops, various types of labs,
administrative offices, conference rooms, and reproduction facilities. A new
roof-mounted substation and additional air handler units were added. The new
facilities required 24-hour air conditioning with uninterruptible power. Project
design was designed to be ADA and Title 24 compliant.
|